Dubai Canal: ‘Parallel’ Sheikh Zayed Road takes shape before October 25 diversion deadline

The upcoming Sheikh Zayed Road diversions have gathered steam as work commenced on the bypass stretch that will serve as a new artery when the current six-lane highway closes to traffic.

Image may be NSFW.
Clik here to view.

[Picture Courtesy: Rajive Singh]


Work on laying a new road in the direction of Abu Dhabi began on September 20, near Al Safa Park, with sources close to the project maintaining the groundwork should complete over the next four weeks.

Image may be NSFW.
Clik here to view.

[Picture Courtesy: Rajive Singh]

In July, Dubai’s Roads and Transport Authority announced the road diversions will take place on Sheikh Zayed Road from October 25.

Image may be NSFW.
Clik here to view.
[Picture Courtesy: Joseph George]

The Dh2-billion Dubai Canal project will result in Sheikh Zayed Road eventually being elevated by a bridge to allow the extension of Dubai Canal to cross on its way to the Arabian Gulf, resulting in 12 lanes of one of the busiest roads of the emirate to be temporarily shifted.

Image may be NSFW.
Clik here to view.

[Picture Courtesy: Rajive Singh]

Maitha bin Udai, CEO of the Traffic and Roads Agency (TRA) at the RTA said in an earlier statement: “Abu Dhabi-bound traffic stream will be routed to the new traffic diversion, while maintaining the traffic movement outbound from the capital by diverting cars to the lanes currently directed in the direction of Abu Dhabi.”

Image may be NSFW.
Clik here to view.

[Picture Courtesy: Rajive Singh]

Parallel to this, the RTA will start construction works on the northern bridge in the direction of Dubai near the Metro line.

Image may be NSFW.
Clik here to view.

[Picture Courtesy: Joseph George]

The project will extend Dubai Creek from Business Bay across Sheikh Zayed Road, through Safa Park and across the two main arteries in Jumeirah to reach the Arabian Gulf.

Image may be NSFW.
Clik here to view.

[Picture Courtesy: Rajive Singh]

Construction on the Dubai Water Canal Project has been split across three phases.

The first includes the construction of bridges across the canal on Sheikh Zayed Road, comprising eight lanes in each direction.

Image may be NSFW.
Clik here to view.

[Picture Courtesy: Rajive Singh]

The bridges will rise eight metres to allow free navigation of water transport vehicles in the canal.

The second phase will see the construction of bridges across the canal, across three lanes on Jumeirah Beach Road and two lanes on Al Wasl Road in each direction.

Image may be NSFW.
Clik here to view.

[Picture Courtesy: Joseph George]

Additionally, a flyover from Al Wasl Road, linking Al Hadiqa Road in the direction of Sheikh Zayed Road will also take form.

Image may be NSFW.
Clik here to view.

[Picture Courtesy: Rajive Singh]

The third and final phase will see the actual construction of the 3.2 km-long canal, with the inclusion of a beach, a marina for boats and the water bus, along with three pedestrian bridges above the canal to link the Jumeirah Beach Walk with Safa Park Walk.

 